Current Projects2020-01-28T14:18:58-07:00

Current Projects

List Of Current Projects
(Organized by most recent project on top)

32162Featured

Airport Trunk Main – Phase 2B

For Whom: City of Prescott

Scheduled Completion Date: February 2021

What's Being Done: Underground Work Including Roadway Improvements

32159Featured

Hoover Dam- Kingman Hwy (US 93) Eleventh St – Windy Pt

For Whom: ADOT

Scheduled Completion Date: October 2020

What's Being Done: Mill & Replace AC Pavement, Shoulder Widening

CMAR Water Production 2139

CMAR Water Production & Pump Station – Design Phase

For Whom: City of Prescott

Scheduled Completion Date: August 2020

What's Being Done: Design and Replacement of Water Booster Facility, and Intermediate Pump Station

2164Featured

Fann New HQ Site and Parking Lot

For Whom: Fann Contracting

Scheduled Completion Date: July 2020

What's Being Done: Civil work for new Fann Contracting headquarters

32148Featured

Meteor Crater – Painted Cliffs Rest Areas

For Whom: ADOT

Scheduled Completion Date: May 2020

What's Being Done: Rehabilitation of Existing Rest Areas off I-40

PRC Prescott Airport Terminal

PRC Prescott Airport New Terminal

For Whom: City of Prescott

Scheduled Completion Date: May 2020

What's Being Done: Utilities infrastructure; Building pad grading; Parking lot grading and paving. Joint Venture: Willmeng/Fann

Zone 16 Tank and Water Main

For Whom: City of Prescott

Scheduled Completion Date: April 2020

What's Being Done: Installation of new water tank, pump station, and water main.

SR89A Sedona Road Work

SR89A Sedona Oak Creek Canyon Road Work

For Whom: ADOT

Scheduled Completion Date: February 2020

What's Being Done: Mill and Pave, Bridge Deck Rehabilitation, Guardrail Replacement, Pavement Markings, Rumble Strips, etc.