Current Projects2018-11-20T15:54:45+00:00

Current Projects

List Of Current Projects
(Organized by most recent project on top)

CMAR Water Production 2139

CMAR Water Production & Pump Station – Design Phase

For Whom: City of Prescott

Scheduled Completion Date: August 2020

What's Being Done: Design and Replacement of Water Booster Facility, and Intermediate Pump Station

Meteor Crater Rest Area Improvement

Meteor Crater – Painted Cliffs Rest Areas

For Whom: ADOT

Scheduled Completion Date: May 2020

What's Being Done: Rehabilitation of Existing Rest Areas off I-40

Liberator Private Development

Liberator Commercial Improvement

For Whom: Private Developer

Scheduled Completion Date: May 2020

What's Being Done: Installation of new utilities. 3rd Generation LLC

PRC Prescott Airport Terminal

PRC Prescott Airport New Terminal

For Whom: City of Prescott

Scheduled Completion Date: May 2020

What's Being Done: Utilities infrastructure; Building pad grading; Parking lot grading and paving. Joint Venture: Willmeng/Fann

Zone 16 Tank and Water Main

For Whom: City of Prescott

Scheduled Completion Date: April 2020

What's Being Done: Installation of new water tank, pump station, and water main.

SR89A Sedona Road Work

SR89A Sedona Oak Creek Canyon Road Work

For Whom: ADOT

Scheduled Completion Date: February 2020

What's Being Done: Mill and Pave, Bridge Deck Rehabilitation, Guardrail Replacement, Pavement Markings, Rumble Strips, etc.

2156 ERAU Baseball Field

Embry Riddle New Baseball Field and Road Improvements

For Whom: Embry Riddle Aeronautical University

Scheduled Completion Date: November 2019

What's Being Done: New Baseball Field and Road Improvements on Dobberteen Dr

Jackrabbit I-40 Current

I-40 Jackrabbit Rd to Joseph City

For Whom: ADOT

Scheduled Completion Date: October 2019

What's Being Done: Mill & Fill, Road Reconstruction

Cataract Parks

Ash Fork – Flagstaff Hwy (I-40) Cataract Lake Rd – Parks TI

For Whom: ADOT

Scheduled Completion Date: October 2019

What's Being Done: Highway improvements consisting of milling, paving and bridge deck replacement, guard rails reinstallation.

2149 Bearizona Current Pic

Bearizona Paving & Milling

For Whom: Bearizona Wildlife Park

Scheduled Completion Date: September 2019

What's Being Done: Parking Lot Improvements